Generated from the same member list that draws the frame model and the drawings, so a change in one place changes all three.
Everything to stand the skids, posts, floor, girts, headers, rafters, purlins and fascia, and paint the deck. No metal, no doors, no nest boxes. Check items off as they go in the cart; the list remembers on this phone.
Metal and trim, door and nest hardware, the plywood for the boxes, and the vent screen.
Everything that touches the treated skids or posts is galvanized or stainless. If the 4×6×20 timber is not stocked, two 2×6×20 pressure-treated boards screwed face to face make each skid. Prices are rough estimates to size the trip, not quotes.
| Step | Work | Fastening and checks |
|---|---|---|
| 1 | Set the two 20 ft skids on level blocks, 72 in outside to outside, and square them with two temporary 2×4 spreaders at the coop end and at 120 in. Mark the post centers on the skid tops at 1.75, 60 and 118.25 in from the coop end. | Diagonals equal within 1/4 in over the 120 in coop section. The run end of the skids stays bare. |
| 2 | Cut the six 4×4 posts, 78.5 in for the low (nest) side and 90.5 in for the high (door) side. Screw a post base to each mark, stand the posts, plumb and brace them to the skids with temporary 2×4s. | Post outer faces flush with the skid outer faces at 36 in from center. Tops land at 84 and 96 in above ground. |
| 3 | Bolt the two 2×4 rims to the inner post faces, top edge at 35.5 in above ground. Pre-drill post and rim together. | One 1/2 × 6 bolt per post plus two 3 in screws, 6 bolts total. Level the rims to each other before drilling the far side. |
| 4 | Set the six 62 in joists between the rims at 24 in on center, flush with the rim tops. | Three 3 in screws through the rim into each joist end. Keep the seam joists at 48 and 96 in exactly on center. |
| 5 | Lay the 1/2 in deck in five pieces, 65 in across, with the two seams on the joists at 48 and 96 in. Notch nothing: the deck sits inside the posts. Then glue FRP wall panel over the whole deck with FRP adhesive, same five-piece layout, seams over the plywood seams, and run a bead of silicone along every seam and the edges. This floor is sized for birds and litter, about 7 lb per square foot; it is not meant to be walked on. | 1-5/8 in screws at 8 in along edges, 12 in in the field. Vinyl or two coats of porch paint now, while the floor is open. |
| 6 | Bolt the 2×6 headers to the outer post faces: low side top at 84 in, high side top at 96 in. Cut the two sloped end headers to 76 in with 9.5° ends and bolt them to the end posts, tops running from 84 to 96. | Two bolts per post on the long headers; one bolt plus two 3 in screws at each corner post on the end headers. The header tops are the rafter bearing line, so sight them straight. |
| 7 | Screw the 2×4 girts flat to the outer post faces, 3-1/2 in face out: low wall at 36 and 56 in, high wall at 36 in only, both end walls at 36 and 56 in with the end girts running the full 75 in to cover the long girt ends. Add the pop door jacks and the four nest opening jacks at 10.5, 48, 70.5 and 108 in. | Two 3 in screws at every post crossing. Girt bottoms at the stated heights; the siding bottom lands on the 36 in girt. |
| 8 | Cut the six 2×4 rafters to 100.5 in from 10 ft stock with a 1.5 in seat at each header and 9.5° plumb cuts on the tails: 18 in of tail past the low header face over the nest boxes, 6 in past the high header. Set them at 0.75, 24, 48, 72, 96 and 119.25 in. | Two 3 in screws toenailed at each seat plus a hurricane tie at each header. The long tail is a 2×4 cantilever at 24 in centers, which is fine for snow; keep the seat cut to 1.5 in so the rafter is not weakened at the header. |
| 9 | Lay the five 132 in purlins flat across the rafters at 42, 19, -5, -29 and -53 in from the coop centerline (positive toward the door side), 6 in past the end rafters each way. Hang a fly rafter under the purlin ends at each overhang edge, then run a 2×4 fascia across the rafter tails and fly rafter ends at both eaves, top edge flush with the rafter tops. | Two 3 in screws at each purlin crossing, two through the fascia into each tail. The fascia carries the drip edge and the closure strip; there is no soffit, so the overhang stays open underneath and the rafter-bay vents breathe through it. |
| 10 | Roof: drip edge on the high-eave fascia, then four 10 ft panels cut to 102 in down the slope starting at the run end, overlapping one rib toward the prevailing wind, panel ends 1.5 in past both fascias. Rake trim on the fly rafters, vented closure strip on the low-eave fascia. | Panel screws in every rib at every purlin and along both fascias. Trim the last panel to 24 in cover. |
| 11 | Staple 1/2 in hardware cloth across the rafter bays above both headers from inside, then fit the hinged 1/2 in plywood flap strips below them. Frame and screen the 12 × 24 in window in the run-end wall. | These bays are the whole winter-summer ventilation system; do them before the siding closes the walls. |
| 12 | Siding, vertical ribs: low wall four 48 in panels, the last trimmed to 12 in cover; each end wall two sloped pieces from one 10 ft panel (48.25 to 54.25 and 54.25 to 60.25 tall), 72 in of cover centered on the 75 in wall; high wall gets the door skins, a 5.5 in strip over the header and 3.5 in strips on the post faces, all from the door-panel offcuts. Corner trim covers the ends. | #10 screws with washers in the flat beside each rib at every girt and header, laps one rib away from the weather. Bottom edge 1/2 in below the 36 girt so water drips clear; tops stop at the header tops, leaving the rafter bays open. |
| 13 | Build the two clean-out doors (sheet D1), hang them on the posts with three T-hinges each, hasp to the far post. | 1/4 in gap all round. Doors swing out and down the wall; a hook holds each open. |
| 14 | Build and hang the two nest boxes (sheet D2) on the low wall, one per bay so neither straddles the center post, the pop door (sheet D3) in the run-end wall, and the two roosts on their legs inside. | Nest floors at 40 in, fronts 12 in tall, lids sloped 20° on piano hinges at 58 in with a strip of drip edge above each hinge tucked under the siding. Roosts lift out for cleaning. |
| 15 | Remove the temporary braces and spreaders. The coop is complete; the under-coop wire, run, pockets, hitch and axles attach to the bare skids and posts later without touching it. | Keep the 1/2 in carriage bolt holes clear of the 72 and 108 in marks where the fork pockets will notch the skids. |