A 1-3/4 in shaft runs across the unit in two pillow block bearings bolted to the skid tops. A short 2×2 arm is welded to each end of the shaft, outboard of the skids, with a 16 in wheel on a 3/4 in bolt. One 16 in lug welded to the shaft just inboard of a bearing is the handle for everything: a strap hole at the tip for the winch, a 2×2 socket on the tip for a lever bar, and a 1/2 in pin hole at 6 in that lines up with two holes in a plate on the skid face, one at engaged and one at stowed.
Rotating the shaft 150° swings the wheels down; they touch the ground at about 94°, a little above horizontal, and lift the skids 5.3 in by the time the arms point straight down. There the load passes through the shaft center, no torque is needed to hold it, and the pin takes over. A stop tab under the lug carries the slight over-center push so the pin carries nothing while towing.
Lowering is the reverse: pull the pin, let the unit's weight swing the arms back as the skids settle, and when the skids touch at about 94° the wheels are unloaded. The last 56° to the stow hole moves only the 60 lb of arms and wheels, about 20 lb at the lug tip. The lever bar does that swing by itself; with the winch you push the lug over by hand and pin it.
One module per axle. The coop takes two, one near each end. With the winch option each axle has its own winch; with the bar, one bar serves both.
| Item | Value |
|---|---|
| Shaft center above ground | 7.7 in (5.5 skid + 2.2 bearing) |
| Arm, shaft to axle | 5 in |
| Wheel | 16 in dia, 4.80/4.00-8, 4 ply, 600 lb+ each |
| Lift, engaged | 5.3 in |
| Wheel clearance, stowed | 4.0 in at 150° |
| Design load per axle | 1,200 lb (600 per wheel) |
| Peak torque, arms horizontal | 6,000 in-lb |
| Shaft shear stress, 1-3/4 in | 5,700 psi |
| Twist between arms, 72 in | about 2.3° |
| Strap pull, winch option | about 430 lb peak at arms horizontal, falling to zero at the pin |
| Winch | 2,000 to 2,500 lb hand winch, drum on the shaft centerline |
| Hand push, lever option | about 100 lb as the wheels take the load with the bar just past vertical, falling to zero at the pin; all of it pushing down |
| Lug root stress, 3/8 × 2.5 bar | about 18 ksi |
| Stub axle, 3/4 in grade 8 | 1,500 in-lb bending, well inside rating |
Place the two axles so each carries about half the unit. With the coop's balance point 90 in from the coop end, axles at 10 and 170 in split 2,200 lb nearly evenly; axles at the far ends would put 1,400 lb on the coop-end axle.
| Part | Spec | Qty |
|---|---|---|
| Shaft | 1-3/4 in cold-rolled round bar, 78 in | 1 |
| Pillow blocks | UCP209-28 (1-3/4 in bore), 2.19 in center height | 2 |
| Bearing bolts | 1/2 in galvanized through-bolts, 7 in, with washers | 4 |
| Arms | 2×2×3/16 sq tube, 8 in, 1-13/16 in hole for shaft, 3/4 in hole for axle | 2 |
| Stub axles | 3/4 in grade 8 bolt, 6 in, nylock nut, spacer, washers | 2 |
| Wheels | 16 in pneumatic, 4.80/4.00-8, 3/4 in bore, 4 ply | 2 |
| Lug | 3/8 × 2.5 in flat bar, 18 in, 1-13/16 in hole, 1/2 in pin hole at 6 in, 1/2 in strap hole at 16 in | 1 |
| Bar socket, lever option | 2×2×1/8 sq tube, 8 in, welded on the lug tip | 1 |
| Lever bar, lever option | 1-1/4 in schedule 40 pipe, 72 in, one bar serves both axles | 1 |
| Pin plate | 1/4 in plate, 14 × 16 in, 2 in shaft clearance hole, two 1/2 in pin holes above the skid top, stop tab | 1 |
| Plate bolts | 1/2 in galvanized through-bolts, 7 in | 3 |
| Lock pin | 1/2 in hitch pin with clip, 3 in | 1 |
| Winch, winch option | 2,000 to 2,500 lb hand winch, 2 in × 20 ft strap, snap hook, 40 in from the shaft with the drum 3.5 in below the shaft centerline (bracket on the inner skid face) | 1 |
| Strap anchor | 1/2 in hole at the lug tip, or a 3/8 in shackle | 1 |
Welds: arms to shaft both sides, full around; lug to shaft both sides; stop tab to plate. Drill the arm and lug holes before welding and slide them on in order: arm, bearing, lug, bearing, arm. Grease the bearings; the shaft turns a few times a year, so sealed blocks are fine.
Build the test bed first: two 8 ft lengths of 4×6 PT, 72 in outside to outside, tied with two 2×6 cross members, with the shaft 36 in from one end so the winch lands on the skid. Mount the module, then stack sandbags, lumber or a pallet of blocks on the bed to about 1,200 lb and crank it. That proves the lift, the winch effort and the pin alignment before anything touches the coop.
Check three things on the test: the strap line never passes through the shaft center except at dead center (that is what the drum placement guarantees), the lug reaches the engaged pin hole with the lug on the stop tab, and the effort at arms-horizontal is what you expect: about 430 lb line pull, which is 25 to 35 lb at the handle on a typical 4:1 winch, or about 100 lb on the bar.
When it moves to the coop, the bearing bolts go through the real skids, the pin plate bolts to the inner skid face, and the winch bolts to the skid top beside it. Nothing about the module changes.
A strap can only turn the shaft while its line misses the shaft center. With the drum 10 in above the shaft, the strap line passed through the center when the lug was about 14° short of dead center, so the winch stalled there with 1,450 in-lb still to go. The rule is that the line from the drum through the shaft center must point at the lug's engaged position, so the strap line crosses the center only at dead center, where the torque needed is also zero. With the lug now 5° below horizontal at engaged, that puts the drum 3.5 in below the shaft centerline, 40 in away, on a bracket on the inner skid face. The pull then falls smoothly from about 430 lb with the arms horizontal to nothing at the pin.
| Drive | Peak effort | Stows by itself | Cost per axle | Notes |
|---|---|---|---|---|
| Winch and strap | 25 to 35 lb at the crank | no, push the lug over by hand | $40 to $60 | Easiest effort. One winch per axle. |
| Lever bar and pin | about 100 lb pull | yes | under $20 | Nothing to buy but pipe. Hard pull for 30° in the middle; a second person or a 4 in arm fixes it. |
| Come-along | 30 to 40 lb at the lever | no | $50, shared | Hook between a skid eye at shaft height and the lug. One tool for both axles, nothing mounted. |
| Ratchet wheel and pawl bar | about 100 lb pull | yes | $10 of plate | Plasma-cut 12-tooth wheel on the shaft, pawl on the bar. Short pumping strokes, holds between strokes. Same peak as the bar. |
| 12 V linear actuator | a switch | yes | $100 to $140 | 12 in stroke, 1,500 lb, clevis each end, on a 7 in lug. Swing limited to about 120°, so stowed clearance drops to 3 in. Both axles on one switch. |
| Screw jack as pusher | crank | yes | $50 to $80 | Same geometry as the actuator with a 15 in travel A-frame jack on a pivot bracket. Works, but the pivot bracket is more fab than the winch. |
All of them share the shaft, bearings, arms, wheels and pin plate. The winch and the bar are the two built into the model; pick either or fit both, since the lug already has the strap hole and the socket.